Ryan McCuaig
- Senior Associate
In a previous article, we discussed the statutory right to adjudication under the Housing Grants, Construction and Regeneration Act 1996 (as amended) (the “Construction Act”).
Adjudication has been a central feature of the UK construction industry for over 25 years. Designed to keep cash flowing and projects moving, it provides a rapid, temporarily binding decision on disputes arising under construction contracts.
This article considers (i) how to determine whether a dispute has crystallised (a necessary precondition to adjudication) and (ii) the basic procedural steps that apply in a statutory (and most contractual) adjudication procedure.
Before a party can validly refer a matter to adjudication, there must be a “dispute” that arises “under the contract”. That might seem obvious, but it is one of the most common technical challenges raised in adjudication enforcement proceedings.
The referring party can only refer a single dispute, which must relate to matters under the contract. A party that refers multiple disputes under a single notice is likely to face an immediate challenge to the adjudicator’s jurisdiction.
The Construction Act does not define “dispute”. The meaning has therefore been developed by the courts in a significant number of cases. Some key points include:
A successful challenge to the jurisdiction of the adjudicator based on a dispute not having crystallised can lead to significant irrecoverable expenditure. It is important to take advice before serving a notice of adjudication or when faced with such a notice if there are any questions over crystallisation.
Parties to a construction contract have a statutory right to adjudication (under the Construction Act) regardless of whether this is provided for in the contract itself. Once a dispute has crystallised, either party has the statutory right to refer it to adjudication “at any time”.
The adjudication procedure is governed by:
The process is deliberately fast.
Adjudication begins with service of a Notice of Adjudication. This document must briefly set out:
The Notice defines the adjudicator’s jurisdiction. If it is drafted too narrowly, it may restrict the scope of the decision. If too broad or vague, it may attract jurisdictional challenge. Taking advice at this stage to get the Notice right can prevent wasted expenditure and effort.
The adjudicator must be appointed within 7 days of the Notice. This may occur:
The adjudicator must be impartial and must confirm that they are free from conflicts of interest.
Within 7 days of the Notice of Adjudication, the referring party must serve its Referral Notice.
This is effectively the referring party’s full case. It includes:
Given the compressed timetable, in practice the Referral should be substantially prepared before the Notice of Adjudication is served.
The responding party typically has 7–14 days to serve its Response, although this depends on the adjudicator’s directions.
Further submissions (Reply and Rejoinder) may be permitted. The adjudicator controls procedure and has wide discretion on whether to allow further rounds of submissions.
Unlike litigation, adjudication is not bound by strict rules of evidence. It is intended to be swift and practical.
The adjudicator must reach a decision within 28 days of the Referral Notice (although that is extendable to 42 days with the agreement of the parties).
The decision is binding on an interim basis — it must be complied with immediately. Compliance can only be validly refused on very limited bases (e.g. the adjudicator lacked jurisdiction).
If the losing party does not comply, the successful party can seek enforcement in the courts of Scotland or England and Wales (as applicable).
Adjudication is a powerful tool for resolving construction disputes quickly, particularly payment disputes.
It was intended for parties to be able to represent themselves in adjudication proceedings. However, in practice, it is common for parties to have solicitors and counsel representing them in adjudication proceedings. They can sometimes feel like a court procedure on fast-forward.
Ensuring that a dispute has properly crystallised, framing the Notice carefully, and preparing a robust Referral are the foundations of an effective adjudication strategy.
Our specialist Contentious Construction team regularly represents parties who are referring or responding to adjudications. We pride ourselves on our expertise, industry knowledge and our straightforward advice.
If you have any queries relating to adjudication or any other issues arising from ongoing or previous construction, engineering or energy projects, please contact Ryan McCuaig or a member of our Contentious Construction team.