Getting the property package right: A guide for Scottish renewable energy developers

Getting the property package right: A guide for Scottish renewable energy developers

This article was co-authored by Kyle Dougall, Trainee Solicitor.

 

Scotland's renewable energy sector continues to attract significant levels of investment particularly across the onshore wind, hydro and battery energy storage sectors. As of June 2026, there were 1,253 renewable energy projects in the Scottish planning pipeline, with a potential generating capacity of ~99.4 GW. To put that figure into context, Scotland’s current renewable electricity generation capacity stands at 18.4 GW.

As projects progress towards financial close, however, developers and funders are increasingly recognising that securing planning consent and grid capacity is only part of the equation. A project's property arrangements are equally critical to its successful delivery and long-term viability.

Land rights are often a key focus of lender due diligence in project financing  transactions-. Unresolved access and/or cabling arrangements, restrictive title conditions and outstanding third-party consents can lead to extended due diligence processes, increased transaction costs and delays to funding.

From a lender's perspective, the requirement is clear: the project company must be able to demonstrate that it has secured all necessary rights to construct, operate, maintain and ultimately decommission the development throughout its anticipated lifespan. Developers who address property matters at an early stage are therefore generally better placed to achieve an efficient and timely financial close.

 

Securing site control

For most renewable energy projects, site control is initially secured through an option agreement.

An option agreement enables a developer to secure exclusivity over a development site while planning permissions, environmental assessments, grid connection arrangements and other development workstreams are progressed. Given the significant expenditure incurred during this period, careful consideration should be given to ensuring that the developer’s interest is adequately protected.

Under Scots law, an option agreement generally creates a personal contractual right rather than a real right in land. While the option agreement is binding on the contracting parties, it doesn’t, of itself, confer a registered proprietary interest in the Land Register of Scotland that is automatically binding on successive owners.

This distinction is of considerable importance in the context of large-scale renewable energy projects, where developers may invest substantial sums over a period of several years before exercising the option. Reliance on contractual rights alone may not always provide an adequate level of protection where, for example, the landowner becomes insolvent or seeks to deal with the property in a manner inconsistent with the developer's interests.

Accordingly, developers will often seek protection by requiring the landowner to grant a standard security (fixed charge) in their favour. Once registered in the Land Register of Scotland, the standard security creates a real right and can significantly restrict the landowner's ability to dispose of, lease or otherwise encumber the property without prejudicing the developer's interest.

While registration of a standard security does not convert the option itself into a real right, it can provide an effective mechanism for protecting the developer's position throughout the development phase and can assist in demonstrating the robustness of site control to prospective funders and investors.

 

Ensuring lease structures are capable of supporting project finance

Where a development proceeds under a lease structure, the lease will often constitute one of the project's most important assets and form a key component of the lender's security package.

Project finance lenders won’t solely consider whether a lease has been granted. Rather, they will assess whether the lease contains the provisions necessary to support a long-term financing structure and preserve the value of the project in an enforcement scenario.

Particular attention is commonly given to:

  • rights of access during construction, operation and decommissioning;
  • restrictions on assignation and transfer;
  • the ability of the tenant to grant security over its leasehold interest;
  • lender step-in rights;
  • change of control provisions; and
  • decommissioning and reinstatement obligations.

Experience frequently demonstrates that a lease which is commercially acceptable to the developer and landowner may nonetheless require amendment before it’s considered bankable from a lender's perspective.

 

Access rights and grid connection infrastructure

Some of the most significant property risks arise not within the development site itself but in relation to the land situated between the site and the point of grid connection.

Renewable energy projects routinely require rights over third-party land to facilitate:

  • access for construction and/or maintenance;
  • abnormal load deliveries;
  • underground cable routes;
  • substations and switching infrastructure; and
  • ancillary utility services.

Failure to secure legally robust rights over these areas can materially affect the viability of a project. In practice, lenders will often scrutinise cable route rights and access arrangements with the same degree of rigour as they apply to the development site itself.

Property due diligence should therefore encompass the entirety of the project corridor rather than simply the main project site.

 

Servitudes and wayleaves

In Scotland, servitudes are frequently the preferred mechanism for securing long-term rights over third-party land.

As real rights in land, servitudes bind successors in title and provide a degree of permanence and certainty that contractual arrangements cannot typically replicate. For this reason, servitudes are generally regarded as the most robust means of securing rights relating to access, electricity cables, drainage infrastructure and maintenance activities.

However, servitudes aren’t always available in practice. A particular difficulty arises where the project site is itself held under a lease, given that a leasehold interest cannot generally constitute the benefited property in a servitude.

Where the creation of a servitude is not feasible, a wayleave agreement may provide an acceptable alternative. While a wayleave does not establish a real right in land and may therefore attract greater scrutiny from project funders, it may nevertheless offer a commercially pragmatic solution where timescales or ownership constraints prevent the creation of a servitude.

 

Existing standard securities and heritable creditor consents

One of the most common issues encountered in Scottish renewable energy transactions is the presence of existing standard securities (fixed charges) affecting the development land.

Many rural estates and agricultural holdings are subject to financing arrangements secured against the land. Consequently, the landowner may require the consent of its heritable creditor before granting an option, lease, servitude or other project right.

Failure to identify and address these requirements at an early stage can lead to significant delays. From a lender's perspective, rights granted in breach of restrictions contained within an existing security package may not provide the level of certainty required for project financing purposes.

Developers should therefore seek to identify all standard securities affecting the project at the outset and ensure that any necessary heritable creditor consents are obtained well in advance of key transaction milestones.

In practice, these consents frequently become critical path items in project delivery programmes and shouldn’t be treated as a routine administrative exercise.

 

Restrictive title conditions and competing rights

A comprehensive title review remains a fundamental component of the due diligence process.

Developers should seek to identify any rights or restrictions capable of affecting the development, including:

  • restrictive title conditions;
  • mineral reservations;
  • existing utility infrastructure;
  • telecommunications apparatus;
  • pipeline and drainage rights;
  • third-party access rights;
  • public rights of way;
  • core paths; and
  • competing infrastructure interests.

The presence of historic burdens or third-party rights doesn’t necessarily prevent development from proceeding. However, their existence may require redesign of project infrastructure, negotiation of additional rights, or implementation of mitigation measures to satisfy lender requirements.

Projects located within areas of significant renewable energy activity often present further complexity, as existing cable corridors, substations and network infrastructure may already affect the proposed development area.

 

Rights extending beyond the site boundary

Developers should also consider the extent to which the project may interact with neighbouring land beyond the physical footprint of the development.

For example:

  • turbine blades may oversail adjoining property. This is becoming increasingly pertinent as larger turbines reach the market;
  • construction cranes may require temporary rights within neighbouring airspace; and
  • abnormal load deliveries may necessitate temporary encroachment onto third-party land.

While such matters may appear minor when compared with broader development issues, they can become significant obstacles if not addressed before construction commences.

Early identification and engagement with affected landowners can materially reduce the risk of programme delays and disputes during the construction phase.

 

Laying the foundations for long-term project success

As Scotland's renewable energy sector continues to expand, the complexity of the property arrangements underpinning these developments is likely to increase. Larger turbines, evolving technologies, shared infrastructure and competing demands on land will place even greater emphasis on securing comprehensive and legally robust property rights.

For developers, the importance of addressing these matters at an early stage cannot be overstated. A well-structured property package does more than satisfy legal and lender requirements; it provides certainty, reduces the risk of costly delays and helps safeguard the long-term viability of a project.

Ultimately, getting the property arrangements right from the outset is an essential part of delivering a successful renewable energy development. Early engagement with experienced property advisers can help identify potential issues, develop practical solutions and ensure that a project is properly positioned to progress from initial development through to financial close and beyond.

 